During the November 19, 2026 Roosevelt Island Operating Corp (RIOC) Operations Advisory Committee meeting, RIOC Chief Operating Officer Mary Cunneen reported that the $1.3 million project to repair Eleanor’s Pier,

closed since April 2024, is on schedule to re-open by the end of June 2027.
According to Ms Cunneen:
… The project demolition has been completed. The railings, light poles, and decking is complete. There’s been a lot of work in that area. We’ve also secured the required DEC permits in order to get in the water and start doing the pile work that’s needed. Um the schedule’s on track with completion by the end of June in 2027
Ms Cunneen added that the Boat Prow is another story:
… We performed an assessment of the issues there that was completed in August. What we discovered is that new piles would be needed in order to stabilize the structure. This cost would be significant to repair the Prow and I think $2 million is likely on the low side for this project.
According to RIOC President BJ Jones:
The Prow and the North Pier, just to manage expectations, as you may have already determined, is that with the Prow in particular, it’s more complicated and more costly than we would like. And so it’s likely {the repairs} have to be deferred until we can figure out funding from a grant or what have you. We would like to be able to move on that sooner and our fingers are crossed, but you should expect that the North Pier assessment could come back with a similar result….